2018 Bond
- Update #14
- Update #13
- Update #12
- Update #11
- Update #10
- Update #9
- Update #8
- Update #7
- Update #6
- Update #5
- Update #4
- Update #3
- Update #2
- Update #1
Update #14
Gull Lake Center for the Fine Arts Construction Updates
- Project construction continues with the building addition envelope completed to a point where the interior work has progressed with interior finishes going in, the seating subfloor, ect..
- Exterior work has also progressed with the exterior siding work progressing.
- Project completion projected for March 2022.
Gull Lake Center for the Fine Arts Pictures
Update #13
Kellogg Elementary Construction Updates
Completed
- Abatement
- Existing Kellogg Elementary Bldg. Demolition
Under Construction
- New Front Parking Lot/Parent Loop
- Complete New Front Parking Lot/Parent Loop and all Site Restorations.
- Complete Remodel of Media Center.
Traffic Flow
- New Bus Loop will temporarily be used for Parent Drop off/Pick up.
- Buses will temporarily use current Bus Loop in Front of Kellogg Preschool
Kellogg Pictures
Richland Elementary Construction Updates
Completed
- Abatement
- Existing Richland Elementary Bldg. Demolition
Under Construction
- New Front Parking Lot/Parent Loop
- Final Site Restorations and Landscaping in front of School.
- New Staff Parking Lot.
Traffic Flow
- New Parent Loop will be complete for first day of school.
- Buses will use Heather Lane as planned, starting the first day of school.
Richland Pictures
Gull Lake Center For The Fine Arts Construction Updates
- The anticipated completion date is the beginning of March 2022.
Gull Lake Center For The Fine Arts Pictures
Update #12
Kellogg Elementary Project Construction Update
Construction continues to progress well with the new additions along with everything ramping up for the summer work that will begin as soon as the school year has ended. Provided below are the areas of work that will be occurring this summer.
- Demolition of the current Kellogg Elementary Building.
- Construction of the new Parent Loop and the new Parent/Visitor parking lot that will be located in front of the new school.
- Media Center Remodel
The New School will be opened on time this fall with the final work to be completed during the first month of school (September) listed as follows and highlighted in green below:
- The traffic flow for the month of September will be as follows as the project is completed.
- Parents will temporarily use the new back parking lot/bus loop for Parent Drop Off/Pick Up.
- Buses will then be using the current Bus Loop in front of the Kellogg Preschool building.
- The temporary traffic flow will end when the project is completed by October 2021
Kellogg Pictures
Gull Lake Center for the Fine Arts
Project construction continues with the masonry wall construction and structural steel progressing very well. Images of the progress of the construction provided below.
- Project completion projected for January 2022.
Richland Elementary Project Construction Update
Construction continues to progress well with the new additions along with everything ramping up for the summer work that will begin as soon as the school year has ended. Provided below are the areas of work that will be occurring this summer.
- Demolition of the 1956 Classroom wing.
- Construction of the new Parent Loop and the new Parent/Visitor parking lot that will be located in front of the new school.
- Construction of the new Staff Parking Lot.
- Final site restorations.
The New School will be opened on time this fall with the final work to be completed during the first month of school (September) listed as follows and highlighted in green below:
- Staff Parking Lot will be constructed.
- Final site restorations will be completed.
- The traffic flow when school begins next year will be as follows:
- New front parking lot and parent loop completed and ready for use.
- Buses will be staging on Heather Lane near the playground areas as indicated in the image below.
- Project will be completed by October 2021.
Richland Pictures
Gull Lake Center for the Fine Arts Pictures
Update #11
COMPLETED PROJECTS UPDATE
NEW MAINTENANCE BUILDING UPDATE
- School staff has now moved into the New Maintenance Building that is now occupied and operational. Provided below are pictures of the completed project.
RYAN INTERMEDIATE UPDATE
- Ryan Intermediate was completed in September 2020 for the beginning of the 2020/2021 school year. Provided are photos of the completed building additions and site improvements.
PROJECTS UNDER CONSTRUCTION
Kellogg Elementary Project Construction Update
- Construction is progressing well with all trades focusing on the interior areas of the new additions.
- Mechanical and electrical works continues with Boiler installations almost completed.
- Drywall has been completed.
- Painting has begun with the office area receiving the first coat of paint along with classrooms.
- Final polishing of the concrete floors is occurring.
- Tile work is proceeding.
- Casework installations have begun with carpet beginning as soon as the casework is completed.
- Construction Planned over Summer Break:
- Abatement/demolition of existing Kellogg Elementary building.
- New front parking lot/parent loop construction.
- The New School will be opened on time this fall with the final work to be completed during the first month of school (September) listed as follows and highlighted in green below:
- New front parking lot/parent loop
- Final site restorations.
- Media center remodel.
- The traffic flow for the month of September will be as follows as the project is completed.
- Parents will temporarily use the new back parking lot/bus loop for Parent Drop Off/Pick Up.
- Buses will then be using the current Bus Loop in front of the Kellogg Preschool building.
- The temporary traffic flow will end when the project is completed by October 2021.
Richland Elementary Project Construction Update
- Construction is progressing well with all trades focusing on the interior areas of the new additions.
- Mechanical and electrical work continues.
- Drywall has been completed.
- Painting beginning in the classrooms and new office areas.
- Final polishing of the concrete floors is occurring.
- Tile work is proceeding and bathroom fixtures going in.
- Casework installations have begun with carpet beginning as soon as the casework is completed.
- Construction planned over summer break.
- Abatement/demolition of the existing Richland Elementary building.
- New front parking lot/parent loop construction.
- The New School will be opened on time this fall with the final work to be completed during the first month of school (September) listed as follows and highlighted in green below:
- Staff Parking Lot will be constructed.
- Final site restorations will be completed.
- The traffic flow when school begins next year will be as follows:
- New front parking lot and parent loop completed and ready for use.
- Buses will be staging on Heather Lane near the playground areas as indicated in the image below.
- Project will be completed by October 2021.
Gull Lake Center for the Fine Arts
- Project construction has begun with foundations completed and the masonry wall construction beginning.
- Project completion projected for January 2022.
Update #10
Construction Updates
Maintenance Building Construction Update
- New Maintenance Building is completed.
Kellogg Elementary Project Update
- Construction is progressing well with the building additions precast panels completed, structural steel, roof trusses, and metal decking installations are occurring. Concrete floor pours and finishing in progress with interior mechanical and electrical “rough in” work occurring. Steel Stud wall framing also in progress. Primary focus is getting the additions enclosed in before winter weather sets in.
- Project completion projected for October 2021.
Richland Elementary Project Update
- Construction progressing well with the building addition precast panels complete. For the additions the structural steel, roof joist, and metal decking is ongoing. Underground plumbing and prep work for the concrete floor slabs is also in progress within the additions. Primary focus is to get each of the additions enclosed in before winter weather sets in.
- Project completion projected for October 2021.
High School Performing Arts Center
- Project was bid in September 2020 with construction contracts awarded in October 2020. Construction staging areas are now getting set up and construction is beginning.
- Project completion projected for January 2022.
View the full slide show presentation of the Performing Arts Center Virtual Ground Breaking
Outside image of the Performing Arts Center
Performing Arts Center Floor Plan
Interior work bay at the New Maintenance Building
Steel Stud Wall Framing at Kellogg Elementary
Concrete Floors at Kellogg Elementary
Structural steel, roof joist, metal decking at Richland Elementary
Underground plumbing and prep work for the concrete floors
Update #9
Construction Updates
Ryan Intermediate Project Update
- Project is nearing completion with the final project closeout efforts occurring this August 2020. Project completion is on schedule to have Ryan Intermediate ready for the beginning of this upcoming school year.
Kellogg Elementary Project Update
- Construction began in May 2020 with site earthwork and utilities. The last couple of weeks have been primarily focused on the foundations for the new additions.
- Project completion projected for October 2021.
Richland Elementary Project Update
- Construction began in June 2020 with site earthwork and utilities. Foundation work for the new additions began this month. Also completed the work for the east parking lot located between Richland Elementary and the Middle School. The pictures provided show the progress on the foundation work and the parking lot improvements.
- Project completion projected for August 2021.
Maintenance Building Construction Update
- Construction began in May 2020 and much progress has been made over the summer break. Project is near completion with final project closeout occurring this month, August 2020.
Performing Arts Center
- Final construction documents are completed, and the project is going out for bid with final bids due in September 2020.
- Construction scheduled to begin Fall 2020 with completion projected for December 2021.
Foundation Work at Kellogg.
Foundation Work at Kellogg.
Foundation Work at Richland.
Foundation Work at Richland.
Parking Lot Improvements at Richland.
Parking Lot Improvements at Richland.
One of the new extended learning areas at the Ryan Intermediate.
A new mud room at the Ryan Intermediate.
A new classroom at the Ryan Intermediate.
Another new classroom at the Ryan Intermediate.
The new playground at Ryan Intermediate.
The new playground at Ryan Intermediate.
The new playground at Ryan Intermediate.
Maintenance Building.
Maintenance Building.
Performing Arts Center diagram.
Performing Arts Center diagram.
Update #8
Construction Updates
RYAN INTERMEDIATE
- Construction restarted on May 7th, 2020 when the Governor reopened construction activities in the State.
- Trades have begun renovation work in existing building beginning of June.
- Construction in the new classroom additions continues.
- Sidewalks are completed and construction progressing for the playground areas.
- Project is still scheduled to be complete prior to school beginning this Fall, 2020.
MAINTENANCE & STORAGE BLDG.
- Construction started on May 7th, 2020
- Foundations completed, building framing is ongoing.
- Project is projected to be completed early August 2020.
KELLOGG ELEMENTARY
- Construction started on May 7th, 2020
- Demolition of the Maintenance Storage Building is completed.
- Site work prepping for the building addition areas is ongoing.
- New drain field and lift station construction is ongoing.
- Project is projected to be completed prior to school beginning in the Fall 2021.
RICHLAND ELEMENTARY
- Construction started on June 1st, 2020
- Site work has begun with removals of topsoil and earthwork ongoing for the building addition areas.
- Project is projected to be completed prior to school beginning in the Fall 2021.
High School Performing Arts Center
- Final design and development of the construction drawings is ongoing.
- Construction drawings projected to be completed in August 2020.
- Project scheduled to be bid in September 2020
- Construction projected to begin October 2020
- Project is projected to be completed late December 2021/early January 2022
Ryan Extended Learning Area
Maintenance Building
New Kellogg Drain Field
Richland Elementary Addition Site
High School Performing Arts Center
Update #7
Ryan Commons Area
Ryan Classroom
Mudroom between new classrooms
Teacher work room
5th grade wing
Projects Under Construction
Ryan Intermediate – Classroom additions, STEM lab addition, mechanical and electrical system upgrades.
- All additions are on schedule with exterior envelope (walls, windows, and roof) completed.
- Current interior work includes HVAC, lighting and final finishes and casework proceeding.
- Project is scheduled to be completed in time for the beginning of School next fall.
New Maintenance/Storage Building -
- New building with work bays, storage, and facilities for maintenance staff.
- Project construction will start this spring, weather permitting. With the current mild weather construction is getting scheduled to start mid-April 2020.
- Project completion still scheduled for fall 2020.
Kellogg Elementary –
- New K-2 Elementary Building
- Project was bid end of January 2020.
- Construction to begin end of March 2020 with completion projected for October 2021.
Richland Elementary –
- New K-2 Elementary Building
- Project is currently bidding with bids due beginning of April 2020.
- Construction is planned to begin early summer 2020 with completion projected for fall 2021.
High School Performing Arts Center –
- New Auditorium with Support Spaces
- Project is in final design with bidding to occur May/June 2020.
- Construction to begin summer 2020 with completion planned for end of the year 2021.
Update #6
Update #5
Ryan Intermediate
The additions for 4th and 5th grade halls have been completed. Brick has been placed and windows will be installed soon.
- The STEAM labs are underway. Foundations and concrete slabs have been completed and the concrete block walls are under construction. Once concrete block is completed, the exterior brick work will begin.
- The emergency egress tunnel along the exterior of the existing school has been constructed. This “tunnel” will protect any necessary access along the construction zone while building of the concrete block walls is underway.
The foundations and underground work in the 3rd grade hall have been completed. Concrete block walls will begin in the next few weeks.
The new underground Sanitary Sewer lines outside of the 3rd grade hall has been installed and connected. Completion of this work allows normal use of the Ryan Intermediate School to continue while construction moves forward. Allowing for no interruptions to the school.
The new metal stud walls have been installed in the 5th grade hall. The classroom spaces are now defined into individual spaces.
A sample of the polished concrete floor has been completed and is ready for approval
The roof in the 5th grade hall has been installed.
Athletic Project – Construction Complete and currently finishing up project close out items.
·Maintenance/Storage Building – Currently out for bid. Planning to start construction for Project Spring 2020.
Kellogg Elementary – Completing Construction Documents, scheduled to receive bids January 2020 with construction to begin late spring 2020.
Richland Elementary – Design is ongoing, scheduled to receive bids in March 2020 with construction to begin summer 2020.
High School Auditorium – Design is ongoing, scheduled to receive bids in April 2020 with construction to begin late summer 2020.
Update #4
Update #3
2018 Bond Construction Update #3
Jeff Brown -Gull Lake Board of Education Treasurer/Bond ChairThe Gull Lake School Board is excited to share this progress report with you on the construction projects supported by the 2018 Bond. Our Bond Steering Committee is working hard to stay on budget, on time and to complete our projects with the highest possible quality. Our team of GL Board and Staff, along with Kingscott (architects), Miller Davis (construction managers) and the many skilled laborers on the project, are working to meet the expectations of our community and provide an excellent upgrade to our instructional facilities to support all of our students’ success.
As you return to school you will notice that several projects have been completed and others are underway.
- The new stadium lighting, bleacher Improvements, accessible walkways and new fencing around the athletic field should be nearing completion.
- The Ryan Intermediate classroom additions and STEAM lab, along with mechanical and electrical system upgrades, have begun and are scheduled to be completed by fall of 2020.
- The new maintenance/storage building is in redesign with work beginning this fall and an anticipated completion date of summer 2020.
- Kellogg Elementary is currently in design, with bids expected by the end of the year and construction to begin spring of 2020 with a completion date of fall 2021.
- Richland Elementary is also currently in design with bids expected in late winter 2020, construction beginning in late spring/early summer of 2020 and completion at the end of summer 2021.
- The Gull Lake Performing Arts Center design is on track to be completed in late winter of 2020, followed with bidding in spring of 2020. Construction is expected in the late spring/early summer of 2020 with completion by the start of school in the fall of 2021.
As you may note, there will be many projects under construction during the regular school year. Every effort is being made to limit interruption of our normal school operations. Please be aware of the construction zones and take care to follow signage as to caution and restricted areas. Safety during construction for all members of our GL School students, parents and staff, along with the laborers, is our top priority.
New Lights at Football Stadium
Construction at Ryan Intermediate has started
Update #2
2018 Bond Construction Update #2
Jeff Brown -Gull Lake Board of Education Treasurer/Bond Chair
Timeline
- Athletics Package – Bids out now
- Maintenance/Storage – Bid in Spring
- Kellogg & Ryan – Final Design Phase
- Richland & Auditorium – Prelim Designs Completed; Final Designs beginning in the next few months
Kellogg Exterior Front Entrance
Kellogg Exterior Bus Entrance
Ryan Exterior Bus Loop
Ryan Exterior Steam Lab
Ryan Aerial View
Update #1
2018 Bond Construction Update #1
Jeff Brown -Gull Lake Board of Education Treasurer/Bond ChairOn May 6th the Gull Lake community approved a construction bond for the purpose of facility updates within the District. The project includes construction and/or remodeling of Kellogg Elementary, Richland Elementary, Ryan Intermediate, the long awaited High School Performing Arts Auditorium, continued technology updates and smaller projects including maintenance and storage buildings and ADA athletic improvements.
For construction to meet the expectations of the community a structure has been created to solicit input from District staff and leaders, oversee projects, make crucial decisions and align the project scope with the needs identified to be addressed by the project. The Board of Education is the Decision Overseer; this function is exercised primary through the Bond Steering Committee which is chaired by Jeff Brown who is joined by Brad Bagley and Jon Scott from the Board. The Committee also includes acting Superintendent Anderson and other appropriate GL staff as well as architects, construction management and Gull Lake’s owner’s representative. The Core Team is the Process Overseer which focuses on Design and oversees the entire Bond issue. The Design Input Committees which include building Principals, faculty/staff representatives, technical advisors and administration give very specific building and room design input based on current and anticipated future needs to be addressed with the construction project.
To set the time line for construction, multiple factors have been considered. These include; limiting the volume of work bid at one time to allow for bids from a wide variety of contractors, limiting the amount of work under construction at one time to avoid disruption within the District, addressing the needs of Kellogg Elementary early in the construction cycle given the challenging condition of the facility, biding during favorable times of the year to improve competitive bids, minimizing the potential for inequities between Kellogg and Richland Elementary by bidding them near the same time. The goal is to build high quality facilities, meet each time line and construct within the scope of the budget, it is critical to do this with minimal disruption to our students, staff and community.
Based on these and other significant factors the following time line has been approved by the Steering Committee:
- Maintenance and Storage Buildings and Athletic/ADA improvements: Bid Feb 2019, Construction Spring 2019 -Sept 2019
- Kellogg Elementary: Bid Spring 2019, Construction June 2019-August 2020
- Ryan Intermediate: Bid Spring 2019, Construction June 2019-October 2020
- Richland Elementary: Bid September 2019, Construction November 2019-March 2021
- HS Performing Arts Auditorium Bid February 2020, Construction April 2020-July 2021.
Kellogg Elementary was completed for the first day of school 2021. Images of the new main entry below.
SERIES 2 BOND PROJECTS IN DESIGN
The proposed Series 2 Bond Projects are now in design with improvements proposed for the following Facilities: Construction is planned to begin Summer of 2022 and will continue during the Summers of 2023 and 2024.
- High School
- Middle School
- Ryan Intermediate
- Gull Lake Virtual Partnership (Bedford)
- Transportation